Stud and framing calculator

Determine stud count and plate footage for a straight wall.

Measurements

Enter 12′ 6″, 12.5 ft or 3.8 m in a length field.

Calculation scope. Counts studs and plate footage from the spacing and runs you enter. Verify with a licensed professional before choosing member sizes, bracing or load-bearing layouts.

ft if no unit
in if no unit
Studs
25 studs to order

exact 25 studs with 0% waste

Studs
25
Plate material
69 linear ft

Material estimate only. Framing layout and sizes depend on your drawings and applicable code.

Job ticket

Stud and framing
MaterialRaw amountWith wasteTo buy
Studs 25 studs25 studs+0 studs extra 25 studs
Plates 69 ft69 ft+0 ft extra 69 ft
  • Studs

    Raw amount
    25 studs
    With waste
    25 studs+0 studs extra
    To buy
    25 studs
  • Plates

    Raw amount
    69 ft
    With waste
    69 ft+0 ft extra
    To buy
    69 ft
Estimates only. Check with your supplier and local code.

How this is calculated

Round up spaces at the specified spacing and add one end stud plus specified extras. Multiply wall length by the number of plate runs.

Worked example

Wall length: 23 ft · Stud spacing: 16 in · Horizontal plate runs: 3 · Extra studs for ends and openings: 6

  1. Round up spaces at the specified spacing and add one end stud plus specified extras. Multiply wall length by the number of plate runs.
  2. Using those inputs, the primary result is 25.

Sources

Frequently asked questions

What goes into wall length?

Enter the measured or quoted wall length for this job. Follow the unit shown on the field.

How is stud and framing calculator calculated?

Round up spaces at the specified spacing and add one end stud plus specified extras. Multiply wall length by the number of plate runs.

What changes if stud spacing changes?

Enter the new stud spacing and recalculate. Use the full precision shown in the result before transferring it to a dependent estimate.

What should I check before using the result?

Material estimate only. Framing layout and sizes depend on your drawings and applicable code.

How do I build the order?

Check the job ticket for the measured quantity, allowance and the units to order.