Stone veneer mortar calculator
Order scratch-coat mortar and setting-bed mortar by measured area and layer depth.
exact 124.3 ft² with 10% waste
- Net veneer area
- 113 ft²
Job ticket
Stone veneer mortar| Material | Raw amount | With waste | To buy |
|---|---|---|---|
| Scratch coat · 80 lb | 113 ft² | 124.3 ft²+11.3 ft² extra | 8 bagsThickness-adjusted · 17 ft² per bag |
| Setting bed · 80 lb | 3.531 ft³ | 3.884 ft³+0.353 ft³ extra | 6 bags |
-
Scratch coat · 80 lb
- Raw amount
- 113 ft²
- With waste
- 124.3 ft²+11.3 ft² extra
- To buy
- 8 bagsThickness-adjusted · 17 ft² per bag
-
Setting bed · 80 lb
- Raw amount
- 3.531 ft³
- With waste
- 3.884 ft³+0.353 ft³ extra
- To buy
- 6 bags
Order options cover the same work. Choose the package or delivery option you need.
How this is calculated
Use the published scratch-coat coverage at ½ in, adjusted by thickness. Divide the setting-bed area times its measured average depth by mixed yield. Reserve bags separately per phase.
Worked example
85 ft² net; ½ in scratch and ¼ in setting bed, 80 lb bags, no waste.
- The ½ in scratch coat covers about 17 ft² per bag, so reserve 5 bags.
- The setting bed takes 85 × ¼ ÷ 12, about 1.771 ft³.
- At 0.71 ft³ per bag, reserve 3 bags for setting.
Sources
Frequently asked questions
Why are the coats separate?
The scratch coat and setting bed are placed separately and may have different thicknesses.
Can I omit scratch coat?
Enter zero only when your approved assembly omits that layer.
Do I count grout or pointing?
The estimate covers the two bedding layers. Measure and order pointing mortar separately.
What is the setting depth?
Use the average placed thickness under the approved veneer system.
Are these yields exact?
Texture, backing, application and field losses affect consumption.