Add walls and gables, deduct openings, and order siding, starter, corners and trim.
exact 222.2 ft² with 10% waste
- Siding squares before waste
- 2.02 squares
- Siding squares with waste
- 2.222 squares
Job ticket
Siding & trim| Material | Raw amount | With waste | To buy |
|---|---|---|---|
| Siding panels | 202 ft² | 222.2 ft²+20.2 ft² extra | 2 cartons200 ft² installed per carton |
| Starter strip | 43.5 ft | 47.85 ft+4.35 ft extra | 4 sticks |
| J-channel and trim | 38.667 ft | 42.533 ft+3.867 ft extra | 4 sticks |
| Outside corner profiles | 17.5 ft | 19.25 ft+1.75 ft extra | 2 sticks10 ft per profile |
-
Siding panels
- Raw amount
- 202 ft²
- With waste
- 222.2 ft²+20.2 ft² extra
- To buy
- 2 cartons200 ft² installed per carton
-
Starter strip
- Raw amount
- 43.5 ft
- With waste
- 47.85 ft+4.35 ft extra
- To buy
- 4 sticks
-
J-channel and trim
- Raw amount
- 38.667 ft
- With waste
- 42.533 ft+3.867 ft extra
- To buy
- 4 sticks
-
Outside corner profiles
- Raw amount
- 17.5 ft
- With waste
- 19.25 ft+1.75 ft extra
- To buy
- 2 sticks10 ft per profile
Order options cover the same work. Choose the package or delivery option you need.
How this is calculated
Add rectangle, triangle and measured face areas and subtract openings. A siding square is 100 ft². Apply waste to panels and length accessories separately and round cartons and stock pieces once.
Worked example
24 × 10 ft wall minus 25 ft², plus a 24 ft × 5 ft gable. 200 ft² cartons, 31 ft of starter and 22 ft of trim, two 9 ft outside corners, and 10% waste.
- Net area is 240 − 25 + 60 = 275 ft².
- With allowance, plan 302.5 ft², or 3.025 squares. Buy two cartons.
- Buy three 12 ft starter sticks, two 12½ ft trim sticks and two 10 ft corner posts.
Sources
Frequently asked questions
Is one square a carton?
One square is 100 ft². Your carton may contain a different installed area.
What coverage goes into the package box?
Use installed coverage after overlap, as listed for the selected profile.
Can I enter a gable?
Choose Triangular gable and measure its base and perpendicular rise.
Do corners count as siding?
The field panels and corner profiles have separate ticket lines.
Where do I count soffit?
Use a separate material takeoff when soffit uses a different product or carton.